Phase 1 of railways' game-changing freight corridor network will be ready by November

Phase 1 of railways' game-changing freight corridor network will be ready by November
The first phase of the Rs 81,000-crore dedicated rail freight corridors project is likely to be completed in November.
Once thrown open, the western and the eastern corridors will reduce travel time between Delhi and Mumbai and Delhi and Howrah, the two most congested rail routes in the country, for both passengers and goods. The 1,500-km western freight corridor runs from Dadri near Delhi to Jawahar Lal Nehru Port Trust in Mumbai and the 1,800-km eastern corridor is from Ludhiana in Punjab to Dankuni in West Bengal.
“We’ll be making 432 km part of the western corridor and 343 km of the eastern corridor operational by November,” said Anshuman Sharma, managing director, Dedicated Freight Corridor Corporation, an arm of Indian Railways. “All the freight traffic that is currently on the rail routes between Delhi and Mumbai and Delhi and Kolkata would be moved to these corridors in parts to decongest the existing lines.
”The Delhi-Mumbai rail route is highly congested at present because of the high volume of container traffic which slows up the passenger trains. The Delhi-Kolkata rail route, on the other hand, passes through the coal belt of Jharkhand which has a high density of coal carrying trains.
These trains evacuate coal from the mine heads in Jharkhand and bring them to the power plants in northern and western parts of the country. The 3,300 km long corridors being constructed to connect the mainland with the ports on the western and the eastern coasts of the country are scheduled to be fully completed by 2020.
“The second phase of the project will be opened in 2019 and the full construction will wind up in 2020,” Sharma said.The targeted completion of the project, for which work started in 2010, was 2016-17, but it got delayed because of land acquisition hurdles, environment clearances and the slow pace of Indian Railways and the freight corridor corporation. The progress of the project is now being closely monitored by the Prime Minister’s Office, according to officials.
Indian Railways has already acquired over 98% of the 11,000 hectares of land needed for the project and it will pay nearly Rs 15,000 crore as compensation for the land acquired. The construction of the western corridor is being fully funded by the Japanese International Cooperation Agency, which has provided around Rs 33,000 crore as soft loan. The eastern corridor is being partially funded by the World Bank.
Once operational, the corridors will increase the national transporter’s freight carrying capacity to around 2,300 million tonnes, up from 1,200 million tonnes at present, and help reduce cost of freight transportation.
The Economic Times, New Delhi, 02nd May 2018

Comments

Popular posts from this blog

Govt’s gamble on GST cuts: What do the bond and currency markets signal?

  It’s not just humans who suffer from cognitive biases; markets do too. Interestingly, different financial markets exhibit distinct biases, each interpreting events through its own prism of prejudice. Take the recent announcements on GST reforms: equity markets have chosen to view them through the lens of growth, while bond and currency markets are focusing on potential macroeconomic risks—fiscal pressures and current account challenges. So, which lens captures the true pulse?Equity markets may be right in expecting GST reforms to revive consumption, which has remained lacklustre for a while. But the key question remains—will this revival come at the cost of broader macro stability?It is well known that consumption stocks have rallied since the GST rationalisation announcement. But what about bond markets? What signals are they sending since this rejig was announced from the ramparts of the Red Fort?The signs aren't encouraging. Bond prices have slumped and yields have surged sinc...

Luxury carmakers urge clarity on GST rates to boost festive season sales

  A clear picture regarding new GST rates at the earliest will help the overall auto industry, including the luxury car segment, to regain momentum in the ongoing quarter, which generally sees enhanced sales on account of the festive season.The high-powered GST Council, chaired by Finance Minister Nirmala Sitharaman, will meet on September 3-4 to discuss moving to a two-slab taxation.In an interaction with PTI, BMW Group India President and CEO Hardeep Singh Brar said the recent speculation about the change in GST rates has caused uncertainty in the minds of consumers.Consumer interest and demand is strong, but they (prospective buyers) have adopted a wait-and-watch approach, and this delayed decision-making is impacting new vehicle sales at a certain level, he noted."Expediting clarity on GST rates is essential to get back to speed and ensure the auto sector's contribution to economic growth during this quarter is robust," Brar stated.He also hoped that the sustainable p...

Sebi proposes tighter norms for green bond third-party reviewers

  Sebi on Friday said it has proposed to tighten the norms to appoint independent third-party reviewers or certifiers for green debt securities to align them with requirements for other ESG-linked bonds.In a draft circular, Sebi said that the current norms for green bonds, introduced in February 2023, lack detailed requirements around reviewer independence, conflict of interest mitigation, and disclosure standards that are now in place for other ESG-linked securities under a June 2025 circular.The regulator's latest proposal seeks public comments on a revised framework that would bring parity by incorporating comprehensive criteria for third-party certifiers of green bonds on non-convertible securities.Under the proposed norms, issuers of green debt securities will need to appoint reviewers who are independent of their management, directors, and key managerial personnel. These reviewers will be remunerated in a way that prevents any conflicts of interest and possess relevant expert...